Project Schedule
Project Schedule
My Downtown Hagerstown will be completed by December of 2025, and will take place through the following phases of work
PHASE ONE: KICKOFF & BACKGROUND ANALYSIS
(April – May)
Review Existing Plans and Documents
Study Area Site Tour
Demographic/Economic Trend Analysis
Study Area Existing Conditions Analysis
PHASE TWO: COMMUNITY ENGAGEMENT
(May – December)
Launch Project Website
Interactive Online Activities
Online Surveys
Pop-Ups and “On the Ground” Engagement
Key Stakeholder Interviews
Community Visioning Workshop (June 26, 2025)
PHASE THREE: MARKET ANALYSIS
(June – August)
Market Analysis
Market Analysis Technical Memorandum
Community Update Workshop (Late August)
PHASE FOUR: FEASIBILITY & IMPLEMENTATION
(August – December)
Selection of Catalytic Projects
Detailed Feasibility Analysis of Catalytic Projects
Draft Implementation Strategy
Final Report
Developer Pitch Kit
Final Presentation (Mid November)
Plan Adoption Process